| Entryway Estimate Based On A 4' x 5' Entryway | ||
| Ceiling : 20 S/F Floor : 20 S/F Height : 8 Feet | ||
| Entryway | ||
| Entryway Materials | Quantity | Cost |
| Mesh Contractor Bags | 50 | $ 025 |
| Box Of 1000 Wood Screws | 01 Box | $ 030 |
| Box Of 1000 Drywall Screws | 01 Box | $ 030 |
| Tile Glue Motar Floors | 01 50 lb Bag | $ 030 |
| Tile Grout Sanded Floors | 01 Large Bag | $ 030 |
| Tile Sealer | 01 Bottle | $ 020 |
| Tiles | 30 | $ 060 |
| Latex Paintable Caulking | 03 | $ 010 |
| Drywall Water Resistant | 07 | $ 105 |
| Drywall Compound | 01 Large Tub | $ 020 |
| Mesh Drywall Tape | 01 Roll | $ 010 |
| Paper Drywall Tape | 01 Roll | $ 010 |
| Baseboards | 03 Strips | $ 020 |
| Electrical Wiring | 01 | $ 050 |
| Junction Octagon Boxes | 02 | $ 004 |
| Junction Octagon Box Cover | 02 | $ 002 |
| Junction Octagon Locknuts | 01 Box | $ 005 |
| Marrets | 01 Box | $ 005 |
| Electrical Tape | 01 | $ 003 |
| Plug Conduit Box | 01 | $ 004 |
| Plug Cover | 01 | $ 001 |
| Light Switch | 01 | $ 005 |
| Light Switch Conduit Box | 01 | $ 004 |
| Light Switch Cover | 01 | $ 001 |
| Paint Primer | 01 | $ 020 |
| Paint Ceiling | 01 | $ 030 |
| Paint Walls | 01 | $ 040 |
| Paint Baseboards | 01 | $ 030 |
| Paint Roller Refill | 02 | $ 020 |
| Paint Brushes | 03 | $ 030 |
| Main Door Masonite Smooth Door Slab 30in x 80in | 01 | $ 050 |
| Door Hinges | 01 | $ 010 |
| Door Knobs | 01 | $ 020 |
| Light Fixture | 01 | $ 010 |
| Total Cost Without Taxes | $ 744 | |
| Labor ( Based On 1 Men At $45/hr ) | Time = 30 hours | $ 1350 |
| Materials And Labor Total Without Taxes | $ 2094 | |
| Extra's | Varies |